Status of Way Leave Application
Page
SNWay Leave Case No.Proposal ParticularsOrganization NameChainageCPM OfficeReceived DateStatusRemarks (If Any)
25 MAHSR/WL/2022/42Laying of 160mm dia water pipeline of M/s Gujarat Water Supply & Sewerage Board (GWSSB), Karjan at MAHSR Ch. 384+780Gujarat Water Supply & Sewerage Board384+780CPM Vadodara07-12-2022 Approved
Way Leave Approval Conveyed to CPM Office on 19.05.2023
26 MAHSR/WL/2023/51Way Leave Permission of overhead crossing of 400KV M/C (Twin HTLS) New Navsari- Magarwada across MAHSR Ch 207+022 at Endergotta village of Valsad District.PGCIL207+022CPM Surat30-03-2023 Approved
Way Leave Approval Conveyed to CPM Office on 25.10.2023
27 MAHSR/WL/2023/52Way Leave Permission of overhead crossing of 400KV M/C (Twin HTLS) New Navsari- Magarwada across MAHSR Ch 186+144 at Sukhlav village of Valsad DistrictPGCIL186+144CPM Surat30-03-2023 Approved
Way Leave Approval Conveyed to CPM Office on 25.10.2023
28 MAHSR/WL/2023/55Way leave permission for proposed 8” Ø Gas Pipeline along with OFC Cable across MAHSR Corridor from Mothiya SV-2 of DUPL to Amboli Terminal of ABGL in Hansot & Ankleshwar Talukas of Bharuch DistrictGAIL India313+511CPM Surat17-04-2023 Approved
Way Leave Approval Conveyed to CPM Office on 24.11.2023
29 MAHSR/WL/2023/71Way Leave for Overhead Crossing of 765 kV D/C Navsari (New) – Padghe Transmission Line at crossing(POWERGRID Tower Location No.: AP39C/0 to AP39D/0) between MAHSR Ch 210+001PGCIL210+001CPM Surat03-08-2023 Approved
Way Leave Approval Conveyed to CPM Office on 21.02.2024
30 MAHSR/WL/2023/74Way Leave for proposed 66kv Roongta Substation Development, 66KV D/C UG cable line laying from Exis. 220KV Popda S/S to Prop. 66KV Roongta SS (6+2) UG cable line crossing MAHSR Ch 251GETCO251+804CPM Surat10-08-2023 Approved
Way Leave Approval Conveyed to CPM Office on 3.01.2024