Media Brief: Completion of 100 Kms of Pier Work on MAHSR Corridor
Published Date: 31-10-2022

Mumbai-Ahmedabad High Speed Rail Corridor has achieved a milestone of completing 100 kms of pier work in the state of Gujarat (352 Kms).

Other details are as follows:

1. Project Update in Gujarat State

  • Piers have been constructed over a stretch of 100 km
  • Pile has been cast over a length of 193 km
  • 9.2 km of viaduct is completed which includes 2.5 km of continuous viaduct near Navsari and 6.7 km erected at different locations.
  • Girder Casting – 22.7 km girders have been cast and 9.2 km girders have been erected.
  • Construction work have started in full swing all along the alignment passing through 8 districts of Gujarat & DNH.
  • The works on 8 HSR Stations from Vapi to Sabarmati are under various stages of construction.
  • Bridge Works on important rivers viz., Narmada, Tapti, Mahi and Sabarmati is in progress.

2. Land Acquisition Status:

  • Overall: - 97.82%
  • Gujarat: - 98.87%
  • DNH: - 100%
  • Maharashtra: - 95.45%
  • Status of Possession of Land in Maharashtra is 73.83 %



Ms. Sushma Gaur
General Manager,
Public Relations
Email: gm.pr@nhsrcl.in
Phone: 011-26700000/01
Mr. Nishank Bhanu
Senior Manager,
Marketing & Communications
Email: mgr.pr@nhsrcl.in
Phone: 011-26700000/01
Ms. Pooja Singh
Assistant Manager,
Public Relations
Email: am1.pr@nhsrcl.in
Phone: 011-26700000/01
×