Site Map
Skip to Main Content
EN
English
English
Hindi
Gujarati
Marathi
Japanese
NATIONAL HIGH SPEED RAIL CORPORATION LIMITED
नेशनल हाई स्पीड रेल कॉर्पोरेशन लिमिटेड
ABOUT US
ABOUT NHSRCL
VISION & MISSION
BOARD OF DIRECTORS
ANNUAL REPORT
DIRECTORY
SKILL DEVELOPMENT
MAKE IN INDIA
HONORS & AWARDS
IRP, SOCIAL INITIATIVES & CSR
INNOVATION
PROJECT
PROJECT OVERVIEW
BULLET TRAIN STATIONS
SAFETY FEATURES
MAINTENANCE
TECHANICAL DETAILS
SABARMATI HUB
ABOUT HUB
WALK THROUGH VIDEO
FEASIBILITY STUDY REPORT
GRIEVANCE REDRESSAL COMMITTEE NOTICE
SIA/RAP AND IPP REPORTS
SUPPLEMENTAL ENVIRONMENTAL IMPACT ASSESSMENT REPORT
APPLICATION FOR WAY LEAVE & NOC CASES
PROCEDURE ORDER FOR NOC/WAY LEAVE APPLICATION
STATUS OF NOC APPLICATON
STATUS OF WAY LEAVE APPLICATION
LIST OF NODAL OFFICERS
APPLY ONLINE
TENDER
ACTIVE TENDER/NOTICE
AWARDED TENDERS
ARCHIVED TENDERS
TENDER RELATED INFORMATION
NHSRCL ON CPP PORTAL
MISCELLANEOUS
CAREER
CURRENT OPENINGS
VACANCIES FOR DEPUTATION
ENGAGEMENT ON RE-EMPLOYMENT BASIS FOR RETIRED PERSONNEL
CAREER UPDATES
RESULTS
SYLLABUS FOR WRITTEN EXAM
MEDICAL STANDARDS AND FORMS
MEDIA CENTER
MEDIA COVERAGE
NHSRCL PUBLICATION
PROJECT PHOTO BOOK
LATEST VIDEOS
IMAGE GALLERY
SOCIAL MEDIA
TECHNICAL PAPERS
BLOG AND ARTICLES
PRESS RELEASE
VIGILANCE
ABOUT NHSRCL VIGILANCE
INTEGRITY PLEDGE
PUBLICATIONS
RAILWAY BOARD CIRCULARS/MEMORANDUMS
CVC VIGILANCE MANUAL
VIGILANCE AWARENESS WEEK
PHOTO GALLERY
CONTACT US
RTI
CONTACT DETAILS
HOW TO FILE RTI
RTI INFORMATION
DETAILS OF THIRD PARTY AUDIT
EDUCATIONAL VISITS
KEY DETAILS
MEDIA CENTER
MEDIA COVERAGE
NHSRCL PUBLICATION
PROJECT PHOTO BOOK
LATEST VIDEOS
IMAGE GALLERY
SOCIAL MEDIA
TECHNICAL PAPERS
BLOG AND ARTICLES
PRESS RELEASE
Media Brief: Completion of 75 Kms of Pier Work on MAHSR Corridor
Published Date: 12-07-2022
Salient Features of Mumbai-Ahmedabad High Speed Rail Corridor
Total length of the corridor: 508.17 KM
Maximum Operational Speed: 320 Kmph
Time Taken:
2.07 hours (limited stops)
2.58 hours (all stops)
Total number of Stations: 12
Gujarat: 8
Maharashtra: 4
Stations in Gujarat: Vapi, Bilimora, Surat, Bharuch, Vadodara, Anand/Nadiad, Ahmedabad and Sabarmati
Stations in Maharashtra: Mumbai (BKC), Thane, Virar and Boisar
Number of Depots: 3
Gujarat: 2 (Surat & Sabarmati)
Maharashtra: 1 (Thane)
Operational Control Center: Sabarmati
Land Acquisition Status:
Gujarat: Already Acquired 98.81%
Dadra Nagar Haveli: 100%
Maharashtra: Already Acquired – 72.25% (Pvt.-92.8%; Govt.-92.28%; Forest-Nil)
Project Update in Gujarat State and DNH
In Gujarat and Dadra & Nagar Haveli, 100% of Civil and Track contracts for construction of the route i.e. 352 Kms have been awarded to Indian Contractors.
The works on Piles, Foundations, Piers, Pier Caps, casting & erection of Girders for Viaduct & Stations have started in full swing along the alignment passing through 8 districts of Gujarat.
Construction work of Piles, Pile Caps, Open Foundations, Well Foundations, Piers, Pier Caps is in progress in 180 km length.
Viaduct - Substructure: Till date, 157.8 km Piling, 88.4 km Foundation and 75.1 km Pier work has been completed
Special Bridges:
Crossings over National & State Highways, Irrigation Canals and Railways, will be bridged by long span Steel structures. Test Fabrication has been completed in 4 workshops and actual fabrication is in progress.
Bridge Works on important rivers viz., Narmada, Tapti, Mahi and Sabarmati is in progress. Status is tabulated below:
Narmada Bridge
Out of 22, work is in progress on 15 Well foundations
Mahi Bridge
Work is in progress on all 12 Well foundations
Tapti Bridge
Out of 13, work is in progress on 7 Well foundations
Sabarmati Bridge
Geotechnical work completed. Test pile work in progress
Stations & Depot:
The works on all 8 HSR Stations from Vapi to Sabarmati are under various stages of construction.
Surat Depot – All 128 foundations have been completed
Sabarmati Depot – Work has been awarded on 4th Feb’22. Earthwork is in progress
Ms. Sushma Gaur
General Manager,
Public Relations
Email:
gm.pr@nhsrcl.in
Phone:
011-26700000/01
Mr. Nishank Bhanu
Senior Manager,
Marketing & Communications
Email:
mgr.pr@nhsrcl.in
Phone:
011-26700000/01
Ms. Pooja Singh
Assistant Manager,
Public Relations
Email:
am1.pr@nhsrcl.in
Phone:
011-26700000/01
×
External Link
This is an external link, Are you sure you want to Continue?