10th Steel Bridge Launched for Mumbai-Ahmedabad Bullet Train Project
Published Date: 11-10-2025
First Steel Bridge Launched in Ahmedabad District for Bullet Train Project

The Mumbai-Ahmedabad Bullet Train project has achieved a significant milestone with the successful launching of the 10th steel bridge in Ahmedabad, Gujarat. Spanning 60 meters in length, the bridge was launched over a Western Railway facility (laundry) located adjacent to the railway tracks. This marks the first steel bridge launched in Ahmedabad district for the project.

The launching operation was completed with high precision in just 7 hours after months of meticulous planning and preparation.

For transverse launching, the bridge was assembled at a height of 16.5 meters above ground level on temporary trestles and then side-slewed using two semi-automatic jacks of 200-ton capacity each, supported by locking trolleys to ensure stability.

This 485 metric ton bridge, measuring 12 metres in height and 11.4 metres in width, was fabricated at a dedicated workshop in Wardha (Nagpur, Maharashtra) and was transported to Ahmedabad using specially designed trailers. The bridge construction utilized approximately 20360 Tor-Shear Type High Strength (TTHS) bolts, coated with C5 system protective painting and elastomeric bearings for enhanced durability and vibration control.

A temporary platform measuring 35x60 metres was constructed for assembly of the main structure. To strengthen the track beam during transverse movement, additional temporary brackets were installed. In total, 14 skid arrangements were utilised out of which four were specifically for the transverse launching.

Mumbai Ahmedabad Bullet Train viaduct in Ahmedabad will pass through 31 crossings including railway tracks, flyovers, canal, one river bridge crossing at Sabarmati River and six steel bridges. A total 28 steel bridges are planned for the entire corridor, out of which 17 are in Gujarat and 11 in Maharashtra.


Details of Completed Steel Bridges

Sr. No. Location Length (in meters) Weight (in MT)
1 Across National Highway 53, Surat, Gujarat 70 673
2 Over Vadodara-Ahmedabad main line of Indian Railways, near Nadiad, Gujarat 100 1486
3 Over Delhi-Mumbai National Expressway, near Vadodara, Gujarat 230 (130 + 100) 4397
4 Near Silvassa in Dadra & Nagar Haveli 100 1464
5 Over Western Railways, Vadodara, Gujarat 60 645
6 Over two DFCC Tracks and two Western Railways tracks, Surat, Gujarat 100, 60 2040
7 Over two DFCC tracks, near Vadodara, Gujarat 70 674
8 Over DFCC tracks near Bharuch, Gujarat 100 1400
9 Over NH-48, near Nadiad, Gujarat 2 × 100 2884
10 Over Railway Facility (Laundry) in Ahmedabad, Gujarat 60 485

Related Images




Ms. Sushma Gaur
General Manager,
Public Relations
Email: gm.pr@nhsrcl.in
Phone: 011-26700000/01
Mr. Nishank Bhanu
Senior Manager,
Marketing & Communications
Email: mgr.pr@nhsrcl.in
Phone: 011-26700000/01
Ms. Pooja Singh
Assistant Manager,
Public Relations
Email: am1.pr@nhsrcl.in
Phone: 011-26700000/01
×