Media Brief: A 40 meter long bridge over Gorwa - Madhunagar Flyover at Vadodara is completed for Mumbai-Ahmedabad Bullet Train Project on 23rd July 2024
Published Date: 26-07-2024
  • Mumbai-Ahmedabad Bullet Train corridor is crossing over Gorwa-Madhunagar Flyover in Vadodara through elevated viaduct
  • The flyover is located at a distance of approx. 4 kms from Vadodara Bullet Train station towards Ahmedabad
  • With meticulous planning and precision of execution, the launching over the flyover was completed within the block period of 10 days
  • All necessary safety precautions like hard barricading, traffic diversion signages, route diversion information publication, sufficient traffic marshals and lighting in night time etc. were taken into consideration during the launching process in presence of Traffic Police, Vadodara City

Salient Features:

  • Length of the span – 40 meters
  • Number of segments - 17 Nos.
  • Pier height - 18 meters
  • Weight of total span: 1078 MT
  • Height from the flyover: 8.7 meters
  • Width of the flyover - 16 meters

Related Images



A 40 meter long bridge over Gorwa - Madhunagar Flyover at Vadodara is completed for Mumbai-Ahmedabad Bullet Train Project on 23rd July 2024
A 40 meter long bridge over Gorwa - Madhunagar Flyover at Vadodara is completed for Mumbai-Ahmedabad Bullet Train Project on 23rd July 2024

Ms. Sushma Gaur
General Manager,
Public Relations
Email: gm.pr@nhsrcl.in
Phone: 011-26700000/01
Mr. Nishank Bhanu
Senior Manager,
Marketing & Communications
Email: mgr.pr@nhsrcl.in
Phone: 011-26700000/01
Ms. Pooja Singh
Assistant Manager,
Public Relations
Email: am1.pr@nhsrcl.in
Phone: 011-26700000/01
×