  • Work on all three elevated stations — Thane, Virar, and Boisar — is progressing rapidly. The first slab for Virar and Boisar stations has been cast recently.
  • Pier foundations and pier construction are advancing at multiple locations along the alignment. Approximately 44 km of piers have been cast so far.
  • Viaduct construction using full span box girder launching has recently commenced from the Dahanu area in Palghar district.
  • Excavation work for 7 mountain tunnels is currently in progress in Palghar district.
  • Construction has begun on major river bridges including Vaitarna, Ulhas, and Jagani.
  • A 21 km long underground/undersea tunnel — India’s first of its kind — is under construction between the Mumbai Bullet Train underground station at Bandra-Kurla Complex and Shilphata. Out of the total length, 16 km is being constructed using Tunnel Boring Machines (TBM), while the remaining 5 km is through the New Austrian Tunnelling Method (NATM). This includes a 7 km undersea tunnel at Thane Creek.
  • Approximately 4.1 km of tunnel heading has been completed cumulatively from Shilphata and from two concurrent faces at the ADIT portal using NATM.
  • Base slab casting has been completed at both Vikhroli shaft (at a depth of 56 meters) and Sawli shaft (at a depth of 39 meters).
  • Sludge treatment plants are being installed at shaft locations, and the Mahape tunnel lining casting yard is actively producing tunnel lining segments.
  • At the under-construction Mumbai Bullet Train station at Bandra-Kurla Complex, around 80% of excavation work has been completed. Base slab casting at a depth of 100 feet below ground level has already commenced at both ends of the station site.

Related Images



Bullet Train Construction Update in Maharashtra
Bullet Train Construction Update in Maharashtra

Ms. Sushma Gaur
General Manager,
Public Relations
Email: gm.pr@nhsrcl.in
Phone: 011-26700000/01
Mr. Nishank Bhanu
Senior Manager,
Marketing & Communications
Email: mgr.pr@nhsrcl.in
Phone: 011-26700000/01
Ms. Pooja Singh
Assistant Manager,
Public Relations
Email: am1.pr@nhsrcl.in
Phone: 011-26700000/01
×