Status of Way Leave Application
Page
SNWay Leave Case No.Proposal ParticularsOrganization NameChainageCPM OfficeReceived DateStatusRemarks (If Any)
115 MAHSR/WL/2024/3017Way Leave Permission for crossing of 300 mm diameter horizontal borehole for water main pipeline including 250 mm dia M.S.Casing pipe for Water pipeline along the NHSRCL Corridor in Pati Dist : NavsariGujarat Water Supply & Sewerage Board (GWSSB)220.31CPM Surat04-09-2024 U/Process at Site Office
U/Process at Site Office
116 MAHSR/WL/2024/3018Way Leave Permission for crossing of 300 mm diameter horizontal borehole for water main pipeline including 250 mm dia M.S.Casing pipe for Water pipeline along the NHSRCL Corridor in Pati Dist : NavsariGujarat Water Supply & Sewerage Board (GWSSB)219.605CPM Surat04-09-2024 U/Process at Site Office
U/Process at Site Office
117 MAHSR/WL/2024/3019Way Leave Permission to supply treated waste water to Palsana Enviro Protection Limited (PEPL) located at kadodara junction (opp. to McDonald) industrial cluster from Varachha Sewage Treatment Plant under the recycle reuse policy of Govt of GujaratSurat Municipal Corporation265.5CPM Surat10-09-2024 U/Process at Site Office
U/Process at Site Office
118 MAHSR/WL/2025/A-2Way leave Permission for laying of 125 mm dia natural gas PE pipeline for connectivity to ladvi,Ovian,Chedcha & part of Umbhel village at MAHSR Ch.265.924 in Ovian Village Ttaluka Kamrej Distt- SuratGujarat Gas Limited265+924CPM Surat03-07-2025 U/Process at HQ
U/Process at HQ
119 MAHSR/WL/2025/A-18Way leave permission for Overhead Crossing by Powergrid 400 KV D/C Navsari-Magarvada Transmission LinePGCIL155.42CPM Palghar09-07-2025 U/Process at Site Office
U/Process at Site Office
120 MAHSR/WL/2025/A-24The Maharashtra Govt has tasked MMRDA with implementing the 30.28 km Uttan–Virar Sea Link Project (UVSLP) as per its 15.03.2024 resolution. It includes a 24.25 km 4+4 lane sea bridge, 1 km offshore, and two 3+3 lane connectors at Uttan and Virar. The project links Mira Bhayandar, Vasai, and Virar, ending at VME. The Virar Connector crosses the HSR line at Gas Kopri (KM 70+915), requiring a RoB.MMRDA70+897CPM Mumbai17-07-2025 U/Process at HQ
U/Process at HQ