| SN | Way Leave Case No. | Proposal Particulars | Organization Name | Chainage | CPM Office | Received Date | Status | Remarks (If Any) |
|
115
| MAHSR/WL/2024/3017 | Way Leave Permission for crossing of 300 mm diameter horizontal borehole for water main pipeline including 250 mm dia M.S.Casing pipe for Water pipeline along the NHSRCL Corridor in Pati Dist : Navsari | Gujarat Water Supply & Sewerage Board (GWSSB) | 220.31 | CPM Surat | 04-09-2024 |
U/Process at Site Office
|
|
|
116
| MAHSR/WL/2024/3018 | Way Leave Permission for crossing of 300 mm diameter horizontal borehole for water main pipeline including 250 mm dia M.S.Casing pipe for Water pipeline along the NHSRCL Corridor in Pati Dist : Navsari | Gujarat Water Supply & Sewerage Board (GWSSB) | 219.605 | CPM Surat | 04-09-2024 |
U/Process at Site Office
|
|
|
117
| MAHSR/WL/2024/3019 | Way Leave Permission to supply treated waste water to Palsana Enviro Protection Limited (PEPL) located at kadodara junction (opp. to McDonald) industrial cluster from Varachha Sewage Treatment Plant under the recycle reuse policy of Govt of Gujarat | Surat Municipal Corporation | 265.5 | CPM Surat | 10-09-2024 |
U/Process at Site Office
|
|
|
118
| MAHSR/WL/2025/A-2 | Way leave Permission for laying of 125 mm dia natural gas PE pipeline for connectivity to ladvi,Ovian,Chedcha & part of Umbhel village at MAHSR Ch.265.924 in Ovian Village Ttaluka Kamrej Distt- Surat | Gujarat Gas Limited | 265+924 | CPM Surat | 03-07-2025 |
U/Process at HQ
|
|
|
119
| MAHSR/WL/2025/A-18 | Way leave permission for Overhead Crossing by Powergrid 400 KV D/C Navsari-Magarvada Transmission Line | PGCIL | 155.42 | CPM Palghar | 09-07-2025 |
U/Process at Site Office
|
|
|
120
| MAHSR/WL/2025/A-24 | The Maharashtra Govt has tasked MMRDA with implementing the 30.28 km Uttan–Virar Sea Link Project (UVSLP) as per its 15.03.2024 resolution. It includes a 24.25 km 4+4 lane sea bridge, 1 km offshore, and two 3+3 lane connectors at Uttan and Virar. The project links Mira Bhayandar, Vasai, and Virar, ending at VME. The Virar Connector crosses the HSR line at Gas Kopri (KM 70+915), requiring a RoB. | MMRDA | 70+897 | CPM Mumbai | 17-07-2025 |
U/Process at HQ
|
|