| SN | Way Leave Case No. | Proposal Particulars | Organization Name | Chainage | CPM Office | Received Date | Status | Remarks (If Any) |
|
121
| MAHSR/WL/2025/A-36 | Way leave permission for Laying of 66KV U/G cable line with 630 sq.mm. XLPE Power cable from 220KV Navsari Substation to 66KV M/S Sangam Solar One Pvt Ltd. at MAHSR chainage 235+400 and CH235+500 near NH48 at village. Sisodra, ta. & Dist. Navsari | GETCO | 235+500 | CPM Surat | 21-07-2025 |
U/Process at Site Office
|
|
|
122
| MAHSR/WL/2025/A-40 | Way leave permission for crossing of 66KV D/C (6+1), 1Cx630 Sq. MM underground power cable through 2X400 mm dia. and 1X160 mm dia. HDPE pipe under NHSRCL ROW between HSR Pier 489 P17-P18 in favor of GETCO | GETCO | 489.667 | CPM Ahmedabad | 22-07-2025 |
U/Process at HQ
|
|
|
123
| MAHSR/WL/2025/A-44 | plot no. C-5/1011st floor administrative office building near telephone exchange char rasta vapi-396195 | GIDC | 247.6 | CPM Surat | 29-07-2025 |
U/Process at Site Office
|
|
|
124
| MAHSR/WL/2025/A-45 | Way leave Permission for laying of 1170 mm Dia Water Pipeline Crossing at MAHSR Ch.247.600 in Dhabel village of Navsari District. | GETCO | 247.6 | CPM Surat | 09-08-2025 |
U/Process at Site Office
|
|
|
125
| MAHSR/WL/2025/A-47 | Way Leave Permission for laying of 66 kV underground cable line with 630 Sq.mm XLPE Power cable (3+1) from 66 KV Palod SS to 66 KV Vadoli SS crossing at MAHSR at Ch 290+450 village Mulad Taluka Olpad, Distt Surat | GETCO | 290.45 | CPM Surat | 13-08-2025 |
U/Process at Site Office
|
|
|
126
| MAHSR/WL/2025/A-58 | Way leave Permission for Laying of 66 KV S/C Gadva – Sadhana Line with ACSR Panther Conductor & Partly with 1C, 630 SQ MM ( 3+1 ) Underground Cable , Crossing MAHSR Ch. 463 P/19 to 463 P/20. | GETCO | 463 | CPM Vadodara | 08-10-2025 |
U/Process at Site Office
|
|