| SN | Way Leave Case No. | Proposal Particulars | Organization Name | Chainage | CPM Office | Received Date | Status | Remarks (If Any) |
|
67
| MAHSR/WL/2025/A-14 | Way leave permission for construction of 765kV D/C Ahmedabad- Navsari (South Gujarat) transmission line (Part-II) at MAHSR Ch. 307+436 in Aloonj village of Bharuch district. | Powergrid Vataman Transmission Limited (PVTL) | 307+436 | CPM Surat | 08-07-2025 |
Approved
|
|
|
68
| MAHSR/WL/2025/A-15 | Way Leave Permission for Overhead Construction of 765 KV D/C Vataman-Navsari Transmission Line at MAHSR Ch.245+412 in Parthan village of Navsari District. | Powergrid Vataman Transmission Limited (PVTL) | 245+435 | CPM Surat | 08-07-2025 |
Approved
|
|
|
69
| MAHSR/WL/2025/A-16 | Permission for laying of Vadodara Municipal Corporation's M.S. Water Pipeline of 610MM dia. Dodka - Nandesari Road, Crossing NHSRCL line betweeb Pier no. 415P08 and 415P09. | Vadodara Municipal Corporation | 415+253 | CPM Vadodara | 09-07-2025 |
Approved
|
|
|
70
| MAHSR/WL/2025/A-19 | Way Leave Permission for crossing MAHSR track at chainage 123+200 against construction of 132kv Dahanu Jawhar Tr line | MSETCL | 123+193 | CPM Palghar | 12-07-2025 |
Approved
|
|
|
71
| MAHSR/WL/2025/A-31 | Way Leave Permission for laying of 600 mm dia. RCC drainage & sewer pipe line through 1200mm dia between Stations Vatva (VTA) - Maninagar (MAN) on GER-ADI Section by Ahmedabad Municipal Corporation | Ahmedabad Municipal Corporation | 493+733 | CPM Ahmedabad | 21-07-2025 |
Approved
|
|
|
72
| MAHSR/WL/2025/A-33 | Construction of RUB no. 713B, proposed 1x8.5x4.5m precast RCC box connecting to CPOH Vatva between HSR portal pier no. 489 P14-P15 | Western Railways | 489+667 | CPM Ahmedabad | 21-07-2025 |
Approved
|
|